Vision Work Session
Please finalize any pending items within one week to maintain the project schedule. If we do not hear from you, we will move forward with the items presented. If you need more than one week to finalize decisions, please submit a Hold Request or Request for more Information.
DATE: 04/02/2025
LAYOUT/DESIGN DECISIONS:
Hybrid of three plans presented. Kitchen and Great Room of Option A. Primary Bedroom same on all options - approved. Screen porch on southeast corner approved - screened connection to Primary Bedroom. Move garage to create space for 3rd bedroom and Laundry/Pantry next to Kitchen.
PRODUCTS SELECTED:
Induction
Solar Power being considered in lieu of generator
APPROVED ACTIONS TO MOVE FORWARD:
Draw up plan per notes above. Ask planner of the day about storm water management.
PENDING ITEMS:
Storm Water management tract - can solar panels be installed.