Revised Consultant Set
Please finalize any pending items within one week to maintain the project schedule. If we do not hear from you, we will move forward with the items presented. If you need more than one week to finalize decisions, please submit a Hold Request or Request for more Information.
DATE: 09/10/2025
LAYOUT/DESIGN DECISIONS:
Move Shop Door adjacent to bathroom. Move door to shop bathroom and add shop sink north wall of shop bathroom.
PRODUCTS SELECTED:
N/A
APPROVED ACTIONS TO MOVE FORWARD:
Proceed with Engineering.
Reduce Recessed Lighting.
Add floor outlet at Living Room.
PENDING ITEMS: